Construction activities performed during the period of 6/6/2021 – 6/12/2021 are listed below:[pdf-
- Earthwork Operations: Austin Wood
- Cleared ROW and hauled brush off site between Sta 116 and 125 LT & RT
Cleared ROW between Sta 82 and 92 LT & RT (98% complete)
- Earthwork Operations: Jordan Foster
- Continued excavation between Sta 126 and 146 and hauling over burden off site
- Utility Operations: Jordan Foster
- Waterline installation continued between Sta 153 and 99. Complete to Sta 100 (35% total)
- RCP Crew didn’t work on project this week
Anticipated activities for the next week are as follows:
- Earthwork Operations: Austin Wood
- Continue hauling brush from clearing operation of site between STA 82 and 92 (LT & RT)
- Earthwork Operations: Jordan Foster
Continue working subgrade between Sta 126 and 146. Start Lime treatment for same Sta range
- Utility Operations: Jordan Foster
- Start RCP installation at Chapa School Driveway (Fri-Sat)
- Start Culvert A