Construction activities performed during the period of 6/6/2021 – 6/12/2021 are listed below:[pdf-
- Earthwork Operations: Austin Wood
- Cleared ROW and hauled brush off site between Sta 116 and 125 LT & RT
Cleared ROW between Sta 82 and 92 LT & RT (98% complete)