Several projects are well underway in Kyle with plans for some to be completed by the end of August.


Lehman Road, near Lehman High School, construction is 91% complete along with the paving finished. It’s currently closed from Hallie Dr to Bunton Creek Rd. The road is expected to be completed by the end of the month.


Based on pay estimates, the Burleson Road project is currently 83% complete. Paving is complete except for Rodriguez to the roundabout. Traffic signals and lights are in progress. Substantial completion is planned for this month.


The SouthSide Wastewater Improvements Project is 59% complete. One crew is working on the Post Road lift station. The other crews are working on water lines near Public Works and bore at Post Road near I-35.


The Wastewater Treatment Plant expansion is at 5.21% completion. More project information will be posted near trails for residents.


Share
Rate

Paper is not free between sections 1
Check out our latest e-Editions!
Hays Free Press
Hays-Free-Press
News-Dispatch
Watermark SPM Plus Program June 2025
Starlight Symphony June 2025
Visitors Guide 2025
Subscriptions
Watermark SPM Plus Program June 2025
Community calendar 2
Event calendar
Starlight Symphony June 2025
Hays Free Press/News-Dispatch Community Calendar
Austin Ear, Nose & Throat Clinic (footer)