Buda bond projects still moving slowly
Slow but steady is the progress of infrastructure projects under the 2014 Buda bond, with officials estimating completion of Propositions 3, 4 and 5 by 2020.
Proposition 3- Roads
Proposition 3 projects include improvements to Old Goforth Road, Main Street, Main Street at RM 967 and San Antonio Street at Garison Road.
Allan Crozier with HDR Engineering said the Goforth Road improvement project, which includes dedicated left and right turns at Tom Green Elementary, is still ongoing.
“If you&r...